[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112844":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112844,787,1,"单选题","建设工程的保修期自（ ）之日起计算。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","提交竣工验收报告",false,{"key":16,"text":17,"correct":14},"B","发包方规定",{"key":19,"text":20,"correct":14},"C","发包方与承包方约定",{"key":22,"text":23,"correct":24},"D","竣工验收合格",true,"2020版教材P325 建设工程的保修期自竣工验收合格之日起计算。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]