[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112840":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112840,787,1,"单选题","施工机具费的控制措施不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","按施工方案和施工技术措施中规定的机种和数量安排使用",false,{"key":16,"text":17,"correct":14},"B","提高施工机械的利用率和完好率",{"key":19,"text":20,"correct":21},"C","严格控制租赁施工机械的使用",true,{"key":23,"text":24,"correct":14},"D","严格控制机械设备进出场时间","2020版教材P290 本题考查的是施工成本计划的实施。施工机具费的控制措施：按施工方案和施工技术措施中规定的机种和数量安排使用；提高施工机械的利用率和完好率；严格控制对外租赁施工机械，严格控制机械设备进出场时间。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]