[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112837":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112837,787,1,"单选题","（ ）是控制项目成本支出的标准，也是成本管理的目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目考核成本",false,{"key":16,"text":17,"correct":18},"B","项目计划成本",true,{"key":20,"text":21,"correct":14},"C","项目实际成本",{"key":23,"text":24,"correct":14},"D","项目预算成本","2020版教材P291 本题考查的是降低施工成本的措施。项目计划成本：在考核成本基础上，根据工程项目的技术特征、自然地理特征、劳动力素质、设备情况等，由企业法人代表和项目经理签订的内部承包合同规定的标准成本。它是控制项目成本支出的标准，也是成本管理的目标。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]