[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112836":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112836,787,1,"单选题","成本计划编制程序中，确定项目总体成本目标之后，下一步应做的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预测项目成本",false,{"key":16,"text":17,"correct":18},"B","编制项目总体成本计划",true,{"key":20,"text":21,"correct":14},"C","分解成本目标",{"key":23,"text":24,"correct":14},"D","针对成本计划制定相应的控制措施","2020版教材P285 本题考查的是施工成本控制的依据。项目成本计划编制的程序： （1）预测项目成本； （2）确定项目总体成本目标； （3）编制项目总体成本计划； （4）项目管理机构与组织的职能部门根据责任成本范围，分别确定自己的成本目标，并编制相应的成本计划； （5）针对成本计划制定相应的控制措施； （6）由项目管理机构与组织的职能部门负责人分别审批相应的成本计划。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]