[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112828":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112828,787,1,"单选题","在地下设施、文物和资源保护方面，做法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工前应调查清楚地下各种设施",false,{"key":16,"text":17,"correct":14},"B","保证施工场地周边的各类管线、管道、建筑物、构筑物的安全",{"key":19,"text":20,"correct":21},"C","因拆迁需要，可不保证施工场地周边的各类管线、管道、建筑物、构筑物的安全",true,{"key":23,"text":24,"correct":14},"D","施工过程中一旦发现文物，立即停止施工","2020版教材P274 施工前应调查清楚地下各种设施，做好保护计划，保证施工场地周边的各类管线、管道、建筑物、构筑物的安全； 进行地下工程施工或基础挖掘时，如发现化石、文物、电缆、管道、爆炸物等，应立即停止施工，及时向有关部门报告，按有关规定妥善处理后，方可继续施工。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]