[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112826,787,1,"单选题","对于建设单位、监理单位、总包单位等单位的沟通协调，沟通方法应以（ ）为主。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","定期走访",false,{"key":16,"text":17,"correct":14},"B","利用工地宣传工具",{"key":19,"text":20,"correct":14},"C","个别交流",{"key":22,"text":23,"correct":24},"D","会议座谈",true,"2020版教材P269 对于与建设单位、监理单位、总包单位、分包单位、设备材料供应单位的沟通协调，由于双方具有合同约定的明确的权利与义务，沟通协调应以会议座谈为主，个别交流沟通为辅，平等协商，相互沟通，求得共识。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]