[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112823":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112823,787,1,"单选题","绿色施工评价中，单位工程施工阶段评价应由（ ）组织。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","施工单位",{"key":19,"text":20,"correct":21},"C","监理单位",true,{"key":23,"text":24,"correct":14},"D","政府主管部门","2020版教材P276 本题考查的是现场绿色施工措施。评价组织： （1）单位工程绿色施工评价应由建设单位组织，项目部和监理单位参加。 （2）单位工程施工阶段评价应由监理单位组织，建设单位和项目部参加。 （3）单位工程施工批次评价应由施工单位组织，建设单位和监理单位参加。 （4）项目部应组织绿色施工的随机检查，并对目标的完成情况进行评估。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]