[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112821":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112821,787,1,"单选题","项目部对劳务分承包单位协调管理的重点是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工进度的安排",false,{"key":16,"text":17,"correct":14},"B","质量安全制度制定",{"key":19,"text":20,"correct":14},"C","工程资料移交",{"key":22,"text":23,"correct":24},"D","作业计划的安排",true,"2020版教材P271 该题主要考察的是：项目部对分包队伍协调管理的内容，原文是三、项目部对分包队伍协调管理的内容（二）劳务分承包单位3.协调管理的重点。是作业计划的安排、作业面的调整、施工物资的供给、质量管理制度和安全管理制度的执行、劳务费用的支付、分项工程的验收及其资料的形成和生活设施的安排。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]