[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112819":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112819,787,1,"单选题","在下列沟通协调内容中，属于施工现场内部的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计单位图纸交付顺序",false,{"key":16,"text":17,"correct":14},"B","征求监理单位对施工中的意见",{"key":19,"text":20,"correct":21},"C","施工机具的优化配置",true,{"key":23,"text":24,"correct":14},"D","业主提供的设备的交接","2020版教材P267 内部沟通协调的主要内容：1、施工进度计划安排的协调；2、施工生产资源配备的协调；3、工程质量管理的协调；4、施工安全与卫生及环境管理的协调；",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]