[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112800":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112800,787,1,"单选题","关于机电工程项目施工进度偏差分析的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工作的进度偏差大于该工作的自由时差，此偏差对总工序没有影响",false,{"key":16,"text":17,"correct":14},"B","工作的进度偏差大于该工作的自由时差，此偏差必将影响总工期",{"key":19,"text":20,"correct":14},"C","工作的进度偏差等于该工作的自由时差，此偏差对后续工作有影响",{"key":22,"text":23,"correct":24},"D","工作的进度偏差大于该工作的总时差，此偏差必将影响总工期",true,"2020版教材P227 进度偏差是否大于总时差（1）若工作的进度偏差大于该工作的总时差，此偏差将影响后续工作和总工期，必须采取相应的调整措施。 （2）若工作的进度偏差小于或等于该工作的总时差，此偏差对总工期无影响，但它对后续工作的影响程度，则需要通过比较偏差与自由时差的大小来确定。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]