[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112787":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112787,787,1,"单选题","在施工中，项目部及时向材料部门提出调整供料月计划，作为动态供料的依据，是根据（ ）作出的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","材料部门提出一次性计划",false,{"key":16,"text":17,"correct":14},"B","施工图纸、施工进度",{"key":19,"text":20,"correct":14},"C","施工平面图对现场设施的设计",{"key":22,"text":23,"correct":24},"D","工程变更及调整的施工预算",true,"2020版教材P203 （2）在施工中，根据工程变更及调整的施工预算，及时向材料部门提出调整供料月计划，作为动态供料的依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]