[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112770":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112770,787,1,"单选题","室内给水建筑管道工程的施工程序中，管道安装的紧后工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","系统清洗",false,{"key":16,"text":17,"correct":18},"B","系统试验",true,{"key":20,"text":21,"correct":14},"C","防腐绝热",{"key":23,"text":24,"correct":14},"D","竣工验收","2020版教材P128 本题考查的是建筑管道工程施工程序。施工准备→材料验收→配合土建预留、预埋→管道测绘放线→管道支架制作→管道加工预制→管道支架安装→管道安装→系统压力试验→防腐绝热→系统清洗、消毒→系统通水试验。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]