[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112766":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112766,787,1,"单选题","室外排水管网按排水检查井分段试验。试验时间不少于（ ），逐段观察，管接口无渗漏为合格。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30min",true,{"key":16,"text":17,"correct":18},"B","5mim",false,{"key":20,"text":21,"correct":18},"C","24h",{"key":23,"text":24,"correct":18},"D","1.0h","2020版教材P134 室外排水管网按排水检查井分段试验。试验时间不少于30min，逐段观察，管接口无渗漏为合格。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]