[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112765":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112765,787,1,"单选题","卫生器具施工程序中，卫生器具排水管道安装的紧后工序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","给水配件安装",false,{"key":16,"text":17,"correct":14},"B","排水管道安装",{"key":19,"text":20,"correct":21},"C","灌水试验、通水试验",true,{"key":23,"text":24,"correct":14},"D","卫生器具安装","2020版教材P129 卫生器具施工程序： 施工准备→卫生设备及附件验收→卫生器具安装→卫生器具给水配件安装→卫生器具排水管道安装→灌水、通水试验→试运行",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]