[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112754":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112754,787,1,"单选题","卫生器具施工程序中，卫生器具安装的紧后工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","给水配件安装",true,{"key":16,"text":17,"correct":18},"B","排水管道安装",false,{"key":20,"text":21,"correct":18},"C","灌水试验",{"key":23,"text":24,"correct":18},"D","通水试验","2020版教材P129 卫生器具施工程序，卫生器具安装以后是卫生器具给水配件安装",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]