[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112751,787,1,"单选题","在设计不明确时，热水供应系统的水压试验为系统顶点的工作压力加（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.1MPA",true,{"key":16,"text":17,"correct":18},"B","0.2MPA",false,{"key":20,"text":21,"correct":18},"C","0.3MPA",{"key":23,"text":24,"correct":18},"D","0.4MPA","2020版教材P133 热水供应系统安装完毕，管道保温之前应进行水压试验。试验压力应符合设计要求。当设计未注明时，热水供应系统水压试验压力应为系统顶点的工作压力加0.1MPa，同时在系统顶点的试验压力不小于0.3MPa。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]