[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112748":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112748,787,1,"单选题","建筑管道阀门试验要点不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","安全阀应由具备资质的单位进行检定",false,{"key":16,"text":17,"correct":14},"B","闸阀应按规范要求进行强度和严密性试验",{"key":19,"text":20,"correct":21},"C","检验批要求同牌号、同型号、同时生产",true,{"key":23,"text":24,"correct":14},"D","主干管上起切断作用的闭路阀门，应逐个做强度试验和严密性试验","2020版教材P130 本题考查的是建筑管道施工技术要点。阀门安装前，应按规范要求进行强度和严密性试验，试验应在每批（同牌号、同型号、同规格）数量中抽查10%，且不少于一个。安装在主干管上起切断作用的闭路阀门，应逐个做强度试验和严密性试验。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]