[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112733":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112733,787,1,"单选题","室内给水管道工程施工程序中，管道支架制作的紧后工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","管道测绘放线",false,{"key":16,"text":17,"correct":18},"B","管道加工预制",true,{"key":20,"text":21,"correct":14},"C","管道支架安装",{"key":23,"text":24,"correct":14},"D","管道元件安装","2020版教材P128 施工准备→材料验收→配合土建预留、预埋→管道测绘放线→管道支架制作→管道加工预制→管道支架安装→管道安装→系统压力试验→防腐绝热→系统清洗、消毒→系统满水试验。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]