[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112710":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112710,787,1,"单选题","曳引式电梯设备的施工程序，缓冲器和对重装置安装之前的程序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","曳引机和机房其他设备安装",true,{"key":16,"text":17,"correct":18},"B","轿厢组装",false,{"key":20,"text":21,"correct":18},"C","设备进场验收",{"key":23,"text":24,"correct":18},"D","曳引绳安装","2020版教材P172 1.电力驱动的曳引式或强制式电梯施工程序 清理底坑、搭脚手架、井道测量、验收交接—设备进场验收—开箱点件—安装样板 架、放线—轨道安装—轿厢组装―曳引机和机房其他设备安装—缓冲器和对重装置安装—曳引绳安装—厅门安装—电气装置安装—调试验收—试运转。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]