[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112686":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112686,787,1,"单选题","干粉灭火装置的联动控制组件应进行（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","模拟启动试验",true,{"key":16,"text":17,"correct":18},"B","模拟停止试验",false,{"key":20,"text":21,"correct":18},"C","模拟喷气试验",{"key":23,"text":24,"correct":18},"D","模拟切换操作试验","2020版教材P166 本题考查的是消防工程施工技术要求。消防给水管网安装完毕后，应对其进行强度试验、冲洗和严密性试验。固定消防炮灭火系统施工完毕后，应做喷射功能调试。气体灭火系统灭火剂输送管道安装完成后，应进行强度试验和气压严密性试验，并达到合格。气体灭火系统的调试项目应包括模拟启动试验、模拟喷气试验和模拟切换操作试验。干粉灭火装置的联动控制组件应进行模拟启动试验，包括自动模拟启动和手动模拟启动试验。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]