[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112685":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112685,787,1,"单选题","消防验收顺序通常为验收受理、现场检查、现场验收、结论评定和（ ）等阶段。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发出通知",false,{"key":16,"text":17,"correct":14},"B","现场整改",{"key":19,"text":20,"correct":14},"C","资料移交",{"key":22,"text":23,"correct":24},"D","工程移交",true,"2020版教材P169 （2）验收顺序通常为验收受理、现场检查、现场验收、结论评定和工程移交等阶段。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]