[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112676":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112676,787,1,"单选题","消防工程验收后，经工程移交程序，以明确工程的（ ）责任。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","检修保养",false,{"key":16,"text":17,"correct":14},"B","检查整改",{"key":19,"text":20,"correct":21},"C","维护保管",true,{"key":23,"text":24,"correct":14},"D","施工保修","2020版教材P170 5）工程移交公安消防部门组织指挥的消防验收完成后，由建设单位、监理单位和施工单位将整个工程移交给使用单位或生产单位。工程移交包括工程资料移交和工程实体移交两个方面。工程资料移交包括消防工程在设计、施工和验收过程中所形成的技术、经济文件。工程实体移交表明工程的保管要从施工单位转为使用单位或生产单位，并须按工程承包合同约定办理工程实体的移交手续。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]