[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112671":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112671,787,1,"单选题","消火栓系统施工程序中，箱体稳固的紧后工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","支管安装",false,{"key":16,"text":17,"correct":18},"B","附件安装",true,{"key":20,"text":21,"correct":14},"C","管道试压",{"key":23,"text":24,"correct":14},"D","冲洗→系统调试","2020版教材P164 （2）消火栓系统施工程序：施工准备→干管安装→支管安装→箱体稳固→附件安装→管道试压、冲洗→系统调试。因此B为正确选项",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]