[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112664":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112664,787,1,"单选题","通风空调工程系统调试的主要内容不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","风量测定与调整",false,{"key":16,"text":17,"correct":14},"B","单机试运转",{"key":19,"text":20,"correct":21},"C","综合效能测定与调整",true,{"key":23,"text":24,"correct":14},"D","系统无生产负荷联合试运转及调试","2020版教材P149 系统调试包括设备单机试运转及调试，系统非设计满负荷条件下的联合试运转及调试 A选项属于系统非设计满负荷条件下的联合试运转及调试的内容。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]