[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112657":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112657,787,1,"单选题","风与空调系统满负荷条件下的联合试运转及调试的规定，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","系统总风量调试结果与设计风量的允许偏差应为5%",false,{"key":16,"text":17,"correct":14},"B","系统总风量调试结果与设计风量的允许偏差应为10%",{"key":19,"text":20,"correct":14},"C","系统总风量调试结果与设计风量的允许偏差应为0～10%",{"key":22,"text":23,"correct":24},"D","系统总风量调试结果与设计风量的允许偏差应为一5%～+1O%",true,"2020版教材P150 系统总风量调试结果与设计风量的允许偏差应为一5%～+10% 。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]