[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112654,787,1,"单选题","关于通风与空调系统调试，不包括的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设备单机试运转及调试",false,{"key":16,"text":17,"correct":18},"B","综合效能测定及调整",true,{"key":20,"text":21,"correct":14},"C","防排烟系统的测定和调整",{"key":23,"text":24,"correct":14},"D","系统非设计满负荷条件下的联合试转运","2020版教材P149 通风与空调系统安装完毕投入使用前，应进行系统调试，系统调试应包括设备单机试运转及调试、系统非设计满负荷条件下的联合试运转及调试。《通风与空调工程施工质量验收规范》GB 50243-2016取消了综合效能的测定和调整内容。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]