[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112652":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112652,787,1,"单选题","关于空调管道的施工技术要求中，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管道穿楼板和墙体处应设置钢制套管",false,{"key":16,"text":17,"correct":14},"B","管道的连接可采用螺纹连接、焊接、法兰连接或卡箍连接",{"key":19,"text":20,"correct":21},"C","空调冷冻水、制冷剂管道安装完毕后，应进行水压试验",true,{"key":23,"text":24,"correct":14},"D","镀锌钢管采用焊接时，焊缝及热影响区的表面应进行二次镀锌处理","2020版教材P148 空调冷冻水管道安装完毕后，应按设计要求进行强度和严密性试验，采用水压试验；制冷剂管道安装完毕后，应进行吹污，气密性和抽真空试验，按《通风与空调工程施工规范》GB 50738-2011第1 2.2.6条、第15.10.1条、第15.10.2条、第5.1.6条、第15.10.3条规定，吹污和气密性试验均采用洁净干燥空气进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]