[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112650":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112650,787,1,"单选题","通风系统调试的施工程序中，风量平衡调整的紧前工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","风量测试",true,{"key":16,"text":17,"correct":18},"B","测试仪器准备",false,{"key":20,"text":21,"correct":18},"C","流量测试",{"key":23,"text":24,"correct":18},"D","风机设备检查","2020版教材P145 系统调试施工程序，风系统调试程序，风机设备检查→风管，风阀，风口检查→测试仪器仪表准备→风量测试→风量平衡调整→记录测试数据→质量检查",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]