[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112649":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112649,787,1,"单选题","制冷机组的安装程序中，机组运输吊装的紧后工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","机组就位安装",false,{"key":16,"text":17,"correct":18},"B","减振装置安装",true,{"key":20,"text":21,"correct":14},"C","机组配管",{"key":23,"text":24,"correct":14},"D","基础验收","2020版教材P145 制冷机组安装程序，基础验收→冷却塔运输吊装→机组减振装置安装→机组就位安装→机组配置→质量检查",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]