[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112648,787,1,"单选题","通风与空调工程的施工单位通过系统（ ）后即可进入竣工验收。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","测试合格",false,{"key":16,"text":17,"correct":14},"B","设备单机试运转及调整",{"key":19,"text":20,"correct":21},"C","无生产负荷联合试运转及调试",true,{"key":23,"text":24,"correct":14},"D","综合效能测定及调整","2020版教材P149 通风与空调系统安装完毕投入使用前，必须进行系统的试运行与调试，包括设备的单机试运转与调试、系统非设计满负荷下的联合试运行与调试。 2020版教材P150 统非设计满负荷下的联合试运行与调试应在设备单机试运转合格后进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]