[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112643,787,1,"单选题","空调系统带冷（热）源的正常联合试运转，不应少于（ ）小时，当竣工季节与设计条件相差较大时，例如夏季可仅做带冷源的试运转，冬期可仅做带热源的试运转。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","24",false,{"key":16,"text":17,"correct":14},"B","16",{"key":19,"text":20,"correct":14},"C","12",{"key":22,"text":23,"correct":24},"D","8",true,"2020版教材P150 系统非设计满负荷条件下的联合试运转及调试应在设备单机试运转合格后进行。通风系统的连续试运行应不少于2h, 空调系统带冷（热）源的连续试运行应不少于8h。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]