[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112641":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112641,787,1,"单选题","风管系统安装完毕。必须进行严密性检验，严密性检验应（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以主、干管为主",true,{"key":16,"text":17,"correct":18},"B","检验全部工程",false,{"key":20,"text":21,"correct":18},"C","按系统20%比例抽检",{"key":23,"text":24,"correct":18},"D","检验全部支管","2020版教材P148 风管的检验与试验（1）风管系统安装后，必须进行严密性检验，主要检验风管、部件制作加工后的咬口缝、铆接孔、风管的法兰翻边、风管管段之间的连接严密性，检验以主、干管为主，检验合格后方能交付下道工序。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]