[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112637":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112637,787,1,"单选题","风管组对时，风管连接处采用密封材料应满足（ ）的技术条件。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","耐高温",false,{"key":16,"text":17,"correct":14},"B","耐潮湿",{"key":19,"text":20,"correct":21},"C","系统功能",true,{"key":23,"text":24,"correct":14},"D","抗疲劳","2020版教材P147 （二）风管系统的安装要点（2）风管的组对、连接长度应根据施工现场的情况和吊装设备而进行确定。风管连接采用的密封材料应满足系统功能的技术条件。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]