[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112622,787,1,"单选题","关于电动机送电试运行的要求，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","电动机的空载试运行时间宜为2h",false,{"key":16,"text":17,"correct":18},"B","连续启动2次的间隔不应小于3min",true,{"key":20,"text":21,"correct":14},"C","电动机冷却至常温下进行再次启动",{"key":23,"text":24,"correct":14},"D","转向应与设备上运转指示箭头一致","2020版教材P140 电动机试运行： (1)电动机空载试运行时间宜为2h，机身和轴承的温升、电压和电流等应符合建筑设备或工艺装置的空载状态运行要求，并应记录电流、电压、温度、运行时间等有关数据。 (2)接通电源之前就应做好切断电源的准备，以防万一接通电源后，电动机出现不正常的情况时（电动机不能启动、启动缓慢、出现异常声音等）能立即切断电源。 (3)电动机的启动次数不宜过于频繁，连续启动2次的时间间隔不应小于5min，并应在电动机冷却至常温下进行再次启动。 (4)电动机转向应与设备上运转指示箭头一致。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]