[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112602":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112602,787,1,"单选题","电缆敷设施工程序中，电缆敷设紧后工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","电缆搬运",false,{"key":16,"text":17,"correct":18},"B","绝缘测定",true,{"key":20,"text":21,"correct":14},"C","挂标志",{"key":23,"text":24,"correct":14},"D","质量验收","2020版教材P136 室内电缆敷设施工程序：电缆检查→电缆搬运→电缆敷设→电缆绝缘测定→挂标识牌→质量验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]