[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112601,787,1,"单选题","成套配电柜的安装程序中，配电柜安装固定的紧后工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","开箱检查",false,{"key":16,"text":17,"correct":18},"B","母线安装",true,{"key":20,"text":21,"correct":14},"C","小线连接",{"key":23,"text":24,"correct":14},"D","试验调整","2020版教材P135 开关柜、配电柜的安装顺序：开箱检查→二次搬运→基础框架制作安装→柜体固定→母线连接→二次线路连接→试验调整→送电运行验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]