[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112592":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112592,787,1,"单选题","工业炉的烘干应在（ ）进行。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","炉窑砌筑后即可",false,{"key":16,"text":17,"correct":14},"B","炉窑砌筑及相关设备安装结束后",{"key":19,"text":20,"correct":14},"C","单机无负荷试运转后",{"key":22,"text":23,"correct":24},"D","联合试运转后",true,"2020版教材P127 本题考查的是烘炉的技术要求。烘炉应在其生产流程有关的机电设备联合试运转及调整合格后进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]