[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112571,787,1,"单选题","耐火浇筑料施工程序中，膨胀缝填充的紧前工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","模板拆除",true,{"key":16,"text":17,"correct":18},"B","浇筑料振捣",false,{"key":20,"text":21,"correct":18},"C","浇筑料浇筑",{"key":23,"text":24,"correct":18},"D","成品养护","2020版教材P124 2.四。耐火浇筑料施工程序：材料检查验收→施工面清理→锚固钉焊接→模板制作安装→防水剂涂刷→浇筑料搅拌并制作试板→浇筑料浇注并振捣→拆除模板→膨胀预留及填充→成品养护。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]