[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112553":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112553,787,1,"单选题","温度取源部件安装在合金管道拐弯处时，错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在防腐、衬里、和压力试验前安装",false,{"key":16,"text":17,"correct":14},"B","用机械方法开孔",{"key":19,"text":20,"correct":14},"C","逆着物料流向安装",{"key":22,"text":23,"correct":24},"D","取源部件轴线与管道轴线垂直相交",true,"2020版教材P111 本题考查的是自动化仪表取源部件的安装要求。在管道的拐弯处安装时，宜逆着物料流向，取源部件轴线应与管道轴线相重合。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]