[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112532":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112532,787,1,"单选题","仪表工程具备交接验收的条件是开通后连续正常运行（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","72h",false,{"key":16,"text":17,"correct":18},"B","48h",true,{"key":20,"text":21,"correct":14},"C","36h",{"key":23,"text":24,"correct":14},"D","24h","2020版教材P108 （2）仪表工程连续48h开通投入运行正常后，具备交接验收条件。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]