[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112505,787,1,"单选题","球罐散装法施工程序，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","赤道带安装→下寒带安装→下温带安装→上温带安装→上寒带安装",false,{"key":16,"text":17,"correct":14},"B","赤道带安装→下温带安装→上温带安装→下寒带安装→上寒带安装",{"key":19,"text":20,"correct":21},"C","赤道带安装→下温带安装→下寒带安装→上温带安装→上寒带安装",true,{"key":23,"text":24,"correct":14},"D","赤道带安装→上温带安装→上寒带安装→下温带安装→下寒带安装","2020版教材P101 本题考查的是钢制球形储罐安装方法。散装法的施工程序为：支柱上、下段组装→赤道带安装→下温带安装→下寒带安装→上温带安装→上寒带安装→上、下极安装→调整及组装质量总体检查。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]