[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112496":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112496,787,1,"单选题","整装锅炉安装的施工程序中，水压试验之后应做的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","报警及联锁试验",false,{"key":16,"text":17,"correct":18},"B","单机试运转",true,{"key":20,"text":21,"correct":14},"C","热态调试",{"key":23,"text":24,"correct":14},"D","系统试运行","2020版教材P92 本题考查的是锅炉系统主要设备的安装技术要求。整装锅炉安装的主要程序：锅炉基础复查→锅炉设备与技术资料的核对检查→锅炉设备就位找正→附件安装→工艺管路的安装→水压试验→单机试运转→报警及联锁试验→锅炉热态调试与试运转。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]