[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112493":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1112493,787,1,"单选题","发电机转子穿装前应进行单独（ ），消除泄露后再做其他试验。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","液压试验",false,{"key":16,"text":17,"correct":14},"B","气压试验",{"key":19,"text":20,"correct":21},"C","气密性试验",true,{"key":23,"text":24,"correct":14},"D","漏气量试验","2020版教材P90 本题考查的是发电机的安装技术要求。发电机转子穿装前进行单独气密性试验。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]