[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112490":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112490,787,1,"单选题","汽轮机转子安装技术要点不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","转子安装可以分为：转子吊装、转子测量和转子、汽缸找中心",false,{"key":16,"text":17,"correct":18},"B","转子吊装前应进行吊具的200%的工作负荷试验",true,{"key":20,"text":21,"correct":14},"C","转子测量包括轴颈圆度测量",{"key":23,"text":24,"correct":14},"D","转子测量包括转子水平度测量","2020版教材P88 本题考查的是汽轮机的安装技术要求。转子吊装应使用有制造厂提供并具备出厂试验证书的专用横梁和吊索，否则应进行200%的工作负荷试验（时间为1h）。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]