[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112489":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112489,787,1,"单选题","汽轮机凝汽器内部管束进行穿管和连接的时间点是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","低压加热器安装前",false,{"key":16,"text":17,"correct":14},"B","凝汽器壳体管板安装前",{"key":19,"text":20,"correct":14},"C","低压缸就位前",{"key":22,"text":23,"correct":24},"D","低压缸就位后",true,"2020版教材P87 本题考查的是汽轮机的安装技术要求。凝汽器内部设备、部件的安装包括管板、回热系统最后一级低压加热器、管束的安装、连接。凝汽器壳体内的管板、低压加热器的安装，在低压缸就位前就应当完成；管束则可以在低压缸就位之后进行穿管和连接。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]