[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112487":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1112487,787,1,"单选题","风力发电设备的安装程序中，机舱安装的紧后工序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发电机安装",true,{"key":16,"text":17,"correct":18},"B","塔筒安装",false,{"key":20,"text":21,"correct":18},"C","叶轮安装",{"key":23,"text":24,"correct":18},"D","轮毂组合","2020版教材P97 2.风力发电设备的安装程序：施工准备→基础环平台及变频器、电器柜→塔筒安装→机舱安装→发电机安装→叶片与轮毂组合→叶轮安装→其他部件安装→电气设备安装→调试试运行→验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]