[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112470,787,1,"单选题","锅炉本体受热面组合安装的一般程序是：设备清点检查→（ ）→联箱找正划线→管子就位对口、焊接。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","压力试验",false,{"key":16,"text":17,"correct":14},"B","泄漏性试验",{"key":19,"text":20,"correct":14},"C","灌水试验",{"key":22,"text":23,"correct":24},"D","通球试验",true,"2020版教材P94 （1）锅炉本体受热面安装一般程序：设备清点检查—通球试验—联箱找正划线—管子就位对口和焊接。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]