[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112463":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1112463,787,1,"单选题","发电机设备安装的一般程序中，发电机穿转子之后，要做的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","转子水压试验",false,{"key":16,"text":17,"correct":18},"B","氢冷器安装",true,{"key":20,"text":21,"correct":14},"C","励磁机安装",{"key":23,"text":24,"correct":14},"D","气密试验","2020版教材P89 本题考查的是发电机的安装技术要求。发电机设备安装的一般程序：定子就位→定子及转子水压试验→发电机穿转子→氢冷器安装→端盖、轴承、密封瓦调整安装→励磁机安装→对轮复找中心并连接→整体气密试验等。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]