[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112461":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112461,787,1,"单选题","电站汽轮机低压外上缸组合安装正确的程序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","检查水平、垂直结合面间隙→符合要求后试组合→正式组合",false,{"key":16,"text":17,"correct":14},"B","试组合→正式组合→检查水平、垂直结合面间隙",{"key":19,"text":20,"correct":14},"C","检查水平结合面间隙→试组合→检查垂直结合面间隙→符合要求后正式组合",{"key":22,"text":23,"correct":24},"D","试组合→检查水平、垂直结合面间隙→符合要求后正式组合",true,"2020版教材P89 本题考查的是汽轮机的安装技术要求。低压外上缸组合包括：先试组合，以检查水平、垂直结合面间隙，符合要求后正式组合。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]