[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1112458":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1112458,787,1,"单选题","低压缸组合安装中，低压内缸的通流间隙调整工作应在（ ）进行。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","低压内缸就位找正后",false,{"key":16,"text":17,"correct":14},"B","隔板调整前",{"key":19,"text":20,"correct":14},"C","低压转子吊入汽缸前",{"key":22,"text":23,"correct":24},"D","低压转子在汽缸内定位后",true,"2020版教材P89 3）低压内缸组合包括：当低压内缸就位找正、隔板调整完成后，低压转子吊入汽缸中并定位后，再进行通流间隙调整。",{"id":6,"name":27,"category":28,"favorite":29},"二建机电工程实务","建筑工程",0]